Littlemoor House, Oldham

intro

First Choice Homes Oldham (FCHO) committed £2.6m to refurbishing its high-rise properties including Littlemoor House. The investment made the 1970s buildings more energy efficient and compliant with the very latest fire safety regulations, as well as bringing the tower blocks' aesthetics right up to date.



 
image draft 2

Initial inspections of the building showed a concrete substrate. However, on removal of the failed insulation system, it became apparent that three elevations also had a steel frame construction that required a number of structural repairs. Hamilton capably carried out the repairs and worked in partnership with the EWI designers to come up with a completely new solution for these SFS areas. It was decided that Hamilton would install a cavity rail system incorporating fire stops and intumescent strips to form a cavity to install the EWI here. 

Both Hamilton and Casey adapted admirably to changing circumstances on the site. Another challenge facing the project was the COVID-19 UK lockdown which temporarily suspended all activity. The Casey Group acted swiftly and responsibly to ensure that all teams, including Hamilton's 25+ onsite staff, could work safely and the project could get back on track without too much impact overall. 

 
IMG1

Alan Taylor, Operations Director at Casey, said: "It has been fantastic to be part of the Littlemoor and Montgomery House improvement projects and we are delighted with the transformation; it's given these buildings a whole new lease of life."

"Once again, Hamilton has been a pleasure to work with - providing a high spec, compliant EWI solution to meet the client's needs perfectly. The clear and honest communication from the team throughout meant that the project ran as smoothly as possible, and I look forward to working with them again on future contracts."

The housing association engaged The Casey Group Ltd as main contractor to carry out the expansive refurbishment and energy efficiency upgrade package on Littlemoor House. In turn, The Casey Group employed Hamilton (Building Contractors) Ltd to be the external wall insulation (EWI) sub-contractor for this specialist 12-storey job.

Thermal efficiency was boosted for the building's 68 apartments, thanks to a new roofing system and replacement double glazed windows, alongside the new exterior wall insulation: all improvements that should significantly lower heating bills for Littlemoor's 100 residents, who remained in their homes throughout the project. 

When work began, the building had an ageing cladding system in place that needed to be removed and replaced by Hamilton to meet today's more stringent fire safety standards. The company installed Wetherby A2 EWI system which includes limited-combustility stone wool (suitable for buildings of this nature) with a clay brick slip finish to the ground floor and a silicone render finish above. 

Due to the complicated layout of the building, with varying ground levels and large numbers of elevations to be treated, it was established that mast climbers would be the most appropriate and efficient method of access for this project. 

 
img

Hamilton Director Daniel Mackie explains: “Littlemoor House was a really rewarding project. It wasn’t without its challenges – but we’re proud to have helped FCHO and The Casey Group transform this tired and slightly rundown 1970s tower block into a modern, eye-catching building that residents can be proud of.
 
“In fact, residents had a say in choosing the grey and blue shades of the render which have given the building its new and improved look.
 
“Hamilton has partnered with The Casey Group on numerous high rise projects such as this, and we’re always proud to play our part in helping make these buildings smarter and safer for years to come.”
 
One Littlemoor resident told The Oldham Evening Chronicle that “the building looks great – very pleasant and much cleaner… they’ve done a really good job on it. I think it’s a million times better”.

 
img4
Categories: Case Studies

Installer

Hamilton (Building Contractors) Ltd

Hamilton (Building Contractors) Ltd

Unit 7A Sapper Jordan Rossi Park
Baildon
Shipley
BD17 7AX
View case studies Visit website

System holder

Wetherby Building Systems Ltd

Wetherby Building Systems Ltd

Wetherby Building Systems Ltd
1 Kid Glove Road
Golborne
Greater Manchester
WA3 3GS
View case studies Visit website